Laying Boulders

Laying boulders at riverbank

Now that work has begun on stabilising the riverbank of the River Breamish, the project is moving on rapidly. Having finished laying the root wads at Site 1, some boulder-sized material has been placed on top to act as ballast (see the schematic diagram below).

[Credit: The above schematic diagram is copyright © Tweed Forum 2019 and used with permission.]

Some of the actual boulders can be seen in the header image at the top of the page and also in the following photos taken yesterday morning.

The Haywood Contracting team were expecting another delivery of boulders to complete this phase of the works, having started to overfill the root wads plus boulders ‘bund’. This can be seen more clearly in the images below.

Comments

Leave a Reply

XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

By submitting this comment you consent to us processing your personal data in accordance with our Terms of Service and Privacy Policy

Contact Us

Please use the online form...

Contact Us